Out of Sequence Percetage

Member for

22 years 3 months

As You say I would like to see as less as possible.

More than give a percentage on number of activities I think it would be better on volume of work or effort required for the activity. Just to do not have strange peak of reasoruce in my schedule for the next updtae time period.

Just a remind when You have 3 activities A, B, C with finish start link, if for example B start, before A, in the progress You progress B activity good, but You have at least to make a new link f-s between A and C, if You do not want time by time look after the logic.

This could be fine for few time periods, after a revise in the logic I think is necessary, to re-arrange the resources required and not have impossible achievable peak in fron and a better estimation at completion.