As You say I would like to see as less as possible.
More than give a percentage on number of activities I think it would be better on volume of work or effort required for the activity. Just to do not have strange peak of reasoruce in my schedule for the next updtae time period.
Just a remind when You have 3 activities A, B, C with finish start link, if for example B start, before A, in the progress You progress B activity good, but You have at least to make a new link f-s between A and C, if You do not want time by time look after the logic.
This could be fine for few time periods, after a revise in the logic I think is necessary, to re-arrange the resources required and not have impossible achievable peak in fron and a better estimation at completion.
Member for
22 years 11 monthsRE: Out of Sequence Percetage
This thread is not specific to P3 and should be posted in the Project Management Issues Discussion Forum.
Bernard Ertl
InterPlan Systems - eTaskMaker Project Planning Software
Member for
22 years 3 monthsRE: Out of Sequence Percetage
As You say I would like to see as less as possible.
More than give a percentage on number of activities I think it would be better on volume of work or effort required for the activity. Just to do not have strange peak of reasoruce in my schedule for the next updtae time period.
Just a remind when You have 3 activities A, B, C with finish start link, if for example B start, before A, in the progress You progress B activity good, but You have at least to make a new link f-s between A and C, if You do not want time by time look after the logic.
This could be fine for few time periods, after a revise in the logic I think is necessary, to re-arrange the resources required and not have impossible achievable peak in fron and a better estimation at completion.