You need to "construct" different calendars to suit each shift, then allocate the calendars codes to each activity as appropriate (fill cell is useful for this)We have never created different resources for different shifts, because a fitter is still a fitter whether he is on day shift or night shift. If you wish to know how many night shift resources are required, for example, simply use your filter.
Member for
16 years 9 monthsRE: Shift resters using P3
You need to "construct" different calendars to suit each shift, then allocate the calendars codes to each activity as appropriate (fill cell is useful for this)We have never created different resources for different shifts, because a fitter is still a fitter whether he is on day shift or night shift. If you wish to know how many night shift resources are required, for example, simply use your filter.