Primavera Project Planner - P3 Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Thu, 2004-01-15 21:18 Permalink RE: P3 set up enquiry In Tools - Level - splitting, set the maximum number of splits per activity is 0 i.e. no split allowed. Log in or register to post comments
Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Thu, 2004-01-15 21:18 Permalink RE: P3 set up enquiry In Tools - Level - splitting, set the maximum number of splits per activity is 0 i.e. no split allowed.
Member for
23 years 8 monthsRE: P3 set up enquiry
In Tools - Level - splitting, set the maximum number of splits per activity is 0