A couple of things to look at:



1. One option you will need to understand is found under Tools, Options, Autocost Rules. The Freeze Units per time period should be unchecked and then quantities will not change when durations change.



2. Also you need to check the subtract Actuals from ETC or Actuals Quantities will be added to the At Completion and increase the At Completion value.



Regards



Paul E Harris

www.eh.con.au Eastwood Harris Books

Member for

21 years 10 months

yes , of course

Member for

23 years 8 months

have you re-schedule the newtwork after data input?