Please make sure to remove the pointer (path) od any logo file, attachment or graphic. I’m not sure in Suretrek, but in P3, if the software cannot find the fil(s) when open, there is a message box and you need to close it and then remove the link (pointer). Otherwise, the software always search the location of it and low in memory resources.
It’s one of draw back on P3 that backup a project cannot backup the attached. I was told this is resolved in P3e/c (not sure)
sorry i forgot to tell that i have sure track. not p3. also the programmes that i have received fromt the consultants are probably saved using P3. what you think now.
regards
Hashmi
Member for
22 years 8 months
Member for22 years8 months
Submitted by Gilbert Rayco on Mon, 2004-03-01 05:58
i have justed joined in Planning Planet. the topic you are on is some what similar to what i am working on. but the problem i am facing is to change the layout specified in the programme. it appears as if the format of the programme is totally locked. if you make any change in its print preview, header/footers or scales, it just displays illegal function/Report Error.
any one has a clue about it?
Regards
Hashmi
Member for
21 years 10 months
Member for21 years10 months
Submitted by Dinesh Kumar on Sun, 2004-02-29 19:05
I just came from a meeting. Heres how you can do it. Well run it from the sample project APEX and then you can simply do some modifications on the tabular report suggested here to fit your specific project.
1. Open sample project APEX.
2. From the menu, click on: Tools, Tabular Reports, Resource, Tabular.
3. Select RT-02 (Tabular Resource Use - Monthly) and click RUN.
Member for
23 years 8 monthsRE: No Subject Specified
Please make sure to remove the pointer (path) od any logo file, attachment or graphic. I’m not sure in Suretrek, but in P3, if the software cannot find the fil(s) when open, there is a message box and you need to close it and then remove the link (pointer). Otherwise, the software always search the location of it and low in memory resources.
It’s one of draw back on P3 that backup a project cannot backup the attached. I was told this is resolved in P3e/c (not sure)
Member for
16 years 9 monthsRE: No Subject Specified
hi,
thanks for the quick reply,
sorry i forgot to tell that i have sure track. not p3. also the programmes that i have received fromt the consultants are probably saved using P3. what you think now.
regards
Hashmi
Member for
22 years 8 monthsRE: No Subject Specified
Dear Hashmi,
Pls. try to visit this primavera site http://www.primavera.com/support/knowledgebase.html
Pls. note that this will only work if u have valid primavera
maintenance contract.
Rgds,
Gilbert
Member for
16 years 9 monthsRE: No Subject Specified
Hi,
i have justed joined in Planning Planet. the topic you are on is some what similar to what i am working on. but the problem i am facing is to change the layout specified in the programme. it appears as if the format of the programme is totally locked. if you make any change in its print preview, header/footers or scales, it just displays illegal function/Report Error.
any one has a clue about it?
Regards
Hashmi
Member for
21 years 10 monthsRE: No Subject Specified
What luca got is better versions than that
Dinesh
Member for
23 years 8 monthsRE: No Subject Specified
"Auto" files are available on P3 CD under folder RASample...
Member for
21 years 10 monthsRE: No Subject Specified
Hi Luca,
It seems to be you have lot of atomation in your reporting.
I got your excel sheet for resource allocation.Can you please advice or forward if any atomation template you have.
Thank you very much.
Dinesh Kumar
Member for
22 years 3 monthsRE: No Subject Specified
Did You try to set up a automatic reporting in Excel and/or excel using the RA engine capabilities.
You spend a little bit more time at the beginning but after is a matter of just a click
Member for
22 years 5 monthsRE: No Subject Specified
yOU CAN ALSO DO THIS FF THE COMMANDS:
TOOLS=>TABULAR REPORTS=>(RESOURCE or COST)=>LOADING
EXPORT THIS TO csv format. THEN FROM EXCEL YOU CAN DO WHAT YOU WANT.
HOPE THIS HELP
mmd
Member for
22 years 3 monthsRE: No Subject Specified
Hi Aleli,
I just came from a meeting. Heres how you can do it. Well run it from the sample project APEX and then you can simply do some modifications on the tabular report suggested here to fit your specific project.
1. Open sample project APEX.
2. From the menu, click on: Tools, Tabular Reports, Resource, Tabular.
3. Select RT-02 (Tabular Resource Use - Monthly) and click RUN.
This should do the trick.
Best regards,
Jorge