1. Set a new Custom Data Item to Hold the Finish Date of the Free Float Bar. In this case, well Use:
Name = FFBR
Type = F
Length = 7
Description = Free Float Bar
2. Run this statement in a Global Change to calculate the value of FFBR:
&TMP EQ EF + FFL
FFBR EQ &TMP -1
3. Create a new bar:
Start Point = Early Finish
End Point = Free Float Bar (the one we created in Step 1 and manipulated using Global Change in Step 2)
Bar = Dotted Line
Modify Endpoints and Select FFBR (found at the bottom under "Custom data item shapes and colors") Change the shape to a circle and give it a green color. Or whatever shape and color you prefer.
4. Exit it and youre done! If you turn on the Early Bar, Total Float Bar and Free Float Bar, then youll see all three.
I tried this. It works. I hope it works for you, too.
Jorge
Member for
22 years 11 months
Member for23 years
Submitted by Steven Oliver on Mon, 2003-11-17 09:47
In P3 the total float and free float value are available as columns. These are calculated on the predecessor calendar, as is lag.
A bar from the early finish to late finish is by definition the Total Float, and may be created in P3.
A bar from the early finish of an activity to the earliest early start of all successors is the Free Float. This field is NOT available as a standard field in the P3 Bars form and therefore is not a standard option.
A Free float bar is available in SureTrak and I use SureTrak when I am required to produce this bar.
I also recommend any one who has P3 should also have SureTrak as it has a number of good features not available in P3.
Assuming I understand you correctly...all you need to do is select bar under the format heading and add a bar with the parameters of early start and late finish.
Member for
22 years 3 monthsRE: Free float bar
1. Set a new Custom Data Item to Hold the Finish Date of the Free Float Bar. In this case, well Use:
Name = FFBR
Type = F
Length = 7
Description = Free Float Bar
2. Run this statement in a Global Change to calculate the value of FFBR:
&TMP EQ EF + FFL
FFBR EQ &TMP -1
3. Create a new bar:
Start Point = Early Finish
End Point = Free Float Bar (the one we created in Step 1 and manipulated using Global Change in Step 2)
Bar = Dotted Line
Modify Endpoints and Select FFBR (found at the bottom under "Custom data item shapes and colors") Change the shape to a circle and give it a green color. Or whatever shape and color you prefer.
4. Exit it and youre done! If you turn on the Early Bar, Total Float Bar and Free Float Bar, then youll see all three.
I tried this. It works. I hope it works for you, too.
Jorge
Member for
22 years 11 monthsRE: Free float bar
However, using Custom Data Items and Excel, it would be possible to create a custom bar
Member for
24 years 6 monthsRE: Free float bar
In P3 the total float and free float value are available as columns. These are calculated on the predecessor calendar, as is lag.
A bar from the early finish to late finish is by definition the Total Float, and may be created in P3.
A bar from the early finish of an activity to the earliest early start of all successors is the Free Float. This field is NOT available as a standard field in the P3 Bars form and therefore is not a standard option.
A Free float bar is available in SureTrak and I use SureTrak when I am required to produce this bar.
I also recommend any one who has P3 should also have SureTrak as it has a number of good features not available in P3.
Regards
Paul E Harris
Eastwood Harris
Member for
22 yearsRE: Free float bar
Assuming I understand you correctly...all you need to do is select bar under the format heading and add a bar with the parameters of early start and late finish.
Jeff