Logic?

Member for

24 years 5 months

Dear James,

Thats what Im doing now, physically checking the pred start dates and linking the succs manually to the first two.

I think thats the only way, thanks,

Paul.

Member for

16 years 9 months

Hi Paul,



I seem to remember having asked P3 about this one a while back. They had no real answer that could solve the problem, other than by some means of regular "physical" checking of the network, and by adding a logic link at the appropriate time.



Sorry, its not the answer your looking for.



Regards...James

Member for

24 years 5 months

Hi Ali,



That is a good idea, but will only work when two activities are 100% complete. How do I link them for forecasting, which means when the first two are scheduled to be completed, the "A" can proceed?



If B,C,D, or E early starts change due to updatiing how can "A" link itself to the first two of them in early start sequence?

Member for

23 years 9 months

Hi,



As I understand , you have a Conditioned Link.



Suppose activities B,C,D,E,F two of them need to be linked to activity A Just when any two of them has been completed.



To translate the upmentioned statement into Logic fomula:



1-First of all export your program to excel format.the format should have at least the fields"ID,percent progres,Predecessor"



2-in the field of the predecessor you will write for each of the five activities the fomula with if statment"IF %Progress=100 Predecessor=FS".



3-you will need to know how to link Exel files to Primavera.othrewise you will import the file back again to P3 each time you update your progress.