Primavera Project Planner - P3 Member for 8 years 7 months Member for 8 years 7 months Submitted by SteveM on Mon, 2024-10-21 21:06 Permalink Looks like my figures did not Looks like my figures did not post. My question is the same: why must I import the Excel spreadsheet's actual start and finish dates twice before the actual start dates are read in correctly? Log in or register to post comments
Member for 8 years 7 months Member for 8 years 7 months Submitted by SteveM on Mon, 2024-10-21 21:06 Permalink Looks like my figures did not Looks like my figures did not post. My question is the same: why must I import the Excel spreadsheet's actual start and finish dates twice before the actual start dates are read in correctly?