If using the software resource leveling most software longest path and float calculations will be unreliable. P6 calculation of float and longest path break under resource constraints as documented by Oracle and many others. [5][6]
If some relevant constraints such as constraints on renewable resources, consumable resources, spatial resources and conditional logic is missing then the schedule is not reliable. Missing a single schedule constraint might render the schedule not feasible.
Member for
21 years 8 monthsIf using the software
If using the software resource leveling most software longest path and float calculations will be unreliable. P6 calculation of float and longest path break under resource constraints as documented by Oracle and many others. [5][6]
[5] P6 -What are critical path activities?
[6] “Longest Path Value” – TomsBlog
If some relevant constraints such as constraints on renewable resources, consumable resources, spatial resources and conditional logic is missing then the schedule is not reliable. Missing a single schedule constraint might render the schedule not feasible.