What you are describing is what the bar dialogue call the ‘Remaining’ bar. There is no ‘Activity’ bar
If you want to draw a bar from the Early start to Early finish – unaltered by progress the timescale you want in the second column of the barchart dialogue in ‘Plan Bar’
I recommend a wee P6 dates refresher. Google: Ron Winter Primavera Dates
Member for
9 years 8 monthsWhat you are describing is
What you are describing is what the bar dialogue call the ‘Remaining’ bar. There is no ‘Activity’ bar
If you want to draw a bar from the Early start to Early finish – unaltered by progress the timescale you want in the second column of the barchart dialogue in ‘Plan Bar’
I recommend a wee P6 dates refresher. Google: Ron Winter Primavera Dates