Submitted by Zoltan Palffy on Wed, 2019-09-04 13:50
just by changing the project to a deflaut calendar this only applies when adding NEW activities. For all of the existing activities they are still on the original calendar assigned to them. You have to ASSIGN the existing activities to the default calendar. Add a column for calendar, filter for ALL, in the calendar column for the first activity at the top select the default claendar and then do a fill down, now re-schedule your project.
It is ALWAYS a 2 step process adding a calendar does NOTHING until you ASSIGN the activities to that calendar and recalcute the schedule.
Member for
24 years 9 months
Member for24 years9 months
Submitted by Vladimir Liberzon on Mon, 2017-11-20 13:16
Member for
16 years 3 monthsI do what I can to foster our
I do what I can to foster our craft. I am a big fan of Training, Education and Mentoring
I also contribute to the linkedin scheduling forums you can always find me there also.
Member for
16 years 11 monthsHi Guys,Let us all be
Hi Guys,
Let us all be thankful that we are lucky have the great Zoltan in planning project, although there are others great as he is, but his way of sharing his knowledge in both the software and schedulling is just exceptional.
Cheers!
Ruel
Member for
16 years 3 monthsglad I could help
glad I could help
Member for
6 years 2 monthsThank you for the solutins
Thank you for the solutins especially to Zoltan Palffy.
Member for
16 years 3 monthsCalendars are not associated
Calendars are not associated with a wbs, calnedars are assigned to an activity and then the activity is assigned to a WBS.
you determine the durations not the calendars
Member for
7 years 11 monthsI have 3 type of calenders
I have 3 type of calenders allocated for activities.
Default calender which i put is a different one from these 3 calenders.
In my master program from which i imported ,Calender settings were done as stated above.
Member for
7 years 11 monthsHi,Thanks for your Post.In my
Hi,
Thanks for your Post.
In my WBS, activities have three different type calenders are allocated.
So i think , if i give default Calender for all activities,then i wont get same duration.
Please correct me if i am wrong.
Member for
16 years 3 monthsjust by changing the project
just by changing the project to a deflaut calendar this only applies when adding NEW activities. For all of the existing activities they are still on the original calendar assigned to them. You have to ASSIGN the existing activities to the default calendar. Add a column for calendar, filter for ALL, in the calendar column for the first activity at the top select the default claendar and then do a fill down, now re-schedule your project.
It is ALWAYS a 2 step process adding a calendar does NOTHING until you ASSIGN the activities to that calendar and recalcute the schedule.
Member for
24 years 9 monthsDo you level project
Do you level project resources?
Is finish date different also?
Does your project include dependency lags?
Are there multiple calendars?