I WANT TO REMOVE LINK BETWWEN UPDATE PERCENT COMPLETE AND ACTUALS QUANTITY TO DATE BY UNCHECKING THE RULE "USE THE UPDATE PERCENT COMPLETE AGAINST THE BUDGET TO COMPUTE ACTUAL QUANTITY TO DATE." AS I AM THINKIG THAT MAY BE MY ACTIVTY IS 10% COMPLETE BUT THE RSOURCE THAT HAS BEEN USED IS MORE THAN THE RESOURCE BUGETED FOR 10% COMPLETION OF THAT ACTIVIT.
SO I WANT TO GIVE THE RESOURCE UTILIZATION TILL THAT DATE BY MY SELF AND DONT WANT PRIMAVERA TO COMPUTE BY SIMPLY MULTIPLYING PCT COMPLETION TO TOTAL BUDGETED QUANTITY OF THAT ACTIVITY TO CALCULATE VALUES TILL THAT DATE.
Member for
18 years 9 months
Member for18 years9 months
Submitted by Pranab Kumar Deb on Tue, 2008-12-16 04:44
Member for
18 years 9 monthsRE: remove links between % completion and budegted quanty
Ya surely i missed that
Member for
16 years 10 monthsRE: remove links between % completion and budegted quanty
SORRY FOR WRONG NAME SPELL ...DEB
Member for
16 years 10 monthsRE: remove links between % completion and budegted quanty
THANKS FOR THE REPLY DB
I HAD ONE MORE DOUBT:
I WANT TO REMOVE LINK BETWWEN UPDATE PERCENT COMPLETE AND ACTUALS QUANTITY TO DATE BY UNCHECKING THE RULE "USE THE UPDATE PERCENT COMPLETE AGAINST THE BUDGET TO COMPUTE ACTUAL QUANTITY TO DATE." AS I AM THINKIG THAT MAY BE MY ACTIVTY IS 10% COMPLETE BUT THE RSOURCE THAT HAS BEEN USED IS MORE THAN THE RESOURCE BUGETED FOR 10% COMPLETION OF THAT ACTIVIT.
SO I WANT TO GIVE THE RESOURCE UTILIZATION TILL THAT DATE BY MY SELF AND DONT WANT PRIMAVERA TO COMPUTE BY SIMPLY MULTIPLYING PCT COMPLETION TO TOTAL BUDGETED QUANTITY OF THAT ACTIVITY TO CALCULATE VALUES TILL THAT DATE.
Member for
18 years 9 monthsRE: remove links between % completion and budegted quanty
Hello Bilal,
Uncheck " Link remaining duration and schedule percent complete"
so you ca manually enter , Percent complete , remaining duration and resource used
regards
deb