PowerProject users will say theirs is the best system and primavera users will always disagree.
Having used both I will always opt for powerproject - particularly in the field of delay analysis where you have to tell a complex story with simple pictures - simple enough for a judge to understand.
Other benefits in PowerProject which are not in P3 are:
1. Infinite UNDO - REDO feature.
2. Copy Paste into the spreadsheet columns
3. Flexible calendars and work patterns - down to seconds if needed.
4. Border files with embedded activity codes
5. Multiple link colours and curved vertical links.
6. Stunning graphics
etc etc.
A delay analysis in p3 takes 3 times longer than in PowerProject and is about 25% effective.
Fortunately PowerProject has a conversion syatem that takes P3 and produces PowerProject v9 or 10.
It will turn it back again but with startling results as it tries to convert calendars and resources to the much cruder P3 format.
Best regards
Mike T.
Member for
21 years 9 months
Member for21 years9 months
Submitted by Kieran Thomson on Mon, 2008-06-30 09:42
Member for
24 years 6 monthsRE: Power Projects V Premivira?
If you go to:
http://www.astadev.com/software/powerproject/msp/primavera.asp
you may download a pdf that spells it out for you the Asta opinion.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
Member for
19 years 10 monthsRE: Power Projects V Premivira?
Hi All
Lets get back to the original question.
PowerProject users will say theirs is the best system and primavera users will always disagree.
Having used both I will always opt for powerproject - particularly in the field of delay analysis where you have to tell a complex story with simple pictures - simple enough for a judge to understand.
Other benefits in PowerProject which are not in P3 are:
1. Infinite UNDO - REDO feature.
2. Copy Paste into the spreadsheet columns
3. Flexible calendars and work patterns - down to seconds if needed.
4. Border files with embedded activity codes
5. Multiple link colours and curved vertical links.
6. Stunning graphics
etc etc.
A delay analysis in p3 takes 3 times longer than in PowerProject and is about 25% effective.
Fortunately PowerProject has a conversion syatem that takes P3 and produces PowerProject v9 or 10.
It will turn it back again but with startling results as it tries to convert calendars and resources to the much cruder P3 format.
Best regards
Mike T.
Member for
21 years 9 monthsRE: Power Projects V Premivira?
Fight Fight Fight Fight
Member for
22 years 4 monthsRE: Power Projects V Premivira?
Because thats what they are called.
Any more questions?
Member for
17 years 4 monthsRE: Power Projects V Premivira?
Why are you trying to be smart by saying It’s PowerProject and Primavera by the way??
Member for
22 years 4 monthsRE: Power Projects V Premivira?
Emmm, whats yours ?
Member for
17 years 4 monthsRE: Power Projects V Premivira?
whats your point?
Member for
22 years 4 monthsRE: Power Projects V Premivira?
Its PowerProject and Primavera by the way
Member for
22 years 9 monthsRE: Power Projects V Premivira?
James,
have a look at this thread
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=11&Top=2917
there is not much to change after 3 years.
I wrote a white paper on this subject back in 2006, give me your email in a private message if you want it
Alexandre