Planning SOP

Member for

22 years 8 months

Gee planner are getting cranky here !!


Member for

18 years 6 months

Mike,



For people who ask for simple planning guidance the plan must be EXTRA cunning.



In fact, it must be so cunning, you could stick a tale on it and call it a weasel!



Oliver

Member for

19 years 10 months

Hi Oliver



Ok you saw through my cunning plan.



Best regards



Mike T.

Member for

18 years 6 months

10 Activities linked Finish to Start is surely better?

Member for

19 years 10 months

Hi Oliver



Yes this simple activity cascade is the building block for the programme.



Going down the list add suitable descriptions such a Site Clearance - Reduce Level Dig - Piling Mat - Piling etc etc.

Delete surplus activities and summarise the cascade as a sutable location - Block 1 for instance.

Generate the durations using resource modelling.

Copy and paste for other blocks ie Block 1 - 2 - 3 etc.

Summarise all these blocks as Piling works and then go on to the next sequence.

Using this system I can knock out a complex tender programme of 1500 activities in less than 2 days.



Best regards



Mike T.

Member for

18 years 6 months

10 activities linked start to finish?

Member for

19 years 10 months

Hi Oliver



Wrong guess.



This is a quick start up method using powerproject software. I use it all the time.



Best regards



Mike T.

Member for

18 years 6 months

Mike,



I’m guessing this is a joke?



-

-

-

-

Member for

19 years 10 months

Hi Jeric



Start with the basics.



1. Set up a calendar that suits the area’s public holidays.

2. Set up your work pattern that relates to the work hours on site.

3. Set up a resource called "hours" that is modelled on Duration / Gang size. (The hours are to be extracted from the cost plan)

4. Set up the start date on the time bar.

5. Draw one single bar on your chart and allocate the Calendar - Work pattern and resource to it. (give it a duration of 5 days)and call it Activity 1.

6. Copy and paste the activity about 10 times and link them up start to finish.

7. You now have a basic template for any construction programme - this is using the "bottom up" method.

8. Save the file for future use.