As I understand that SAP PS do not have the data date concept. In which case that when you are not updating the entire schedule... As a result, you will have driving activities will not calculated accordingly.
Am I correct??
In addition, I would like to know how many activity is in your individual project Plan... 100s 500s 1000s or 10,000s
Im using SAP PS in planning for building projects. The system is only as good as the data fed into the same. Results are good if the data provided is rich. Methodology is aligned with CPM since all forms of Network logic can be used with lags and leads as necessary. The short-coming is in Reports which also is made up to a large extent by the BI (Business Intelligence) Module. The system can be invaluable if all possible milestones are meticulously fed into the system along with their planned finish dates. The tracking can then be done at ease based on when Actual dates are encountered.
Member for
22 years 8 monthsRE: SAP - PS for planning major project
Gents
As I understand that SAP PS do not have the data date concept. In which case that when you are not updating the entire schedule... As a result, you will have driving activities will not calculated accordingly.
Am I correct??
In addition, I would like to know how many activity is in your individual project Plan... 100s 500s 1000s or 10,000s
Thanks in advance
Alex
Member for
18 years 5 monthsRE: SAP - PS for planning major project
It works best if it is integrated with some project management software like MSP.
Major advantage of using SAP is that you can access all the information of any department at any given moment of time if you are provided read access.
As a project manager, it is of great help.
Cheers,
Ravi
Member for
20 yearsRE: SAP - PS for planning major project
Im using SAP PS in planning for building projects. The system is only as good as the data fed into the same. Results are good if the data provided is rich. Methodology is aligned with CPM since all forms of Network logic can be used with lags and leads as necessary. The short-coming is in Reports which also is made up to a large extent by the BI (Business Intelligence) Module. The system can be invaluable if all possible milestones are meticulously fed into the system along with their planned finish dates. The tracking can then be done at ease based on when Actual dates are encountered.