Level 2 Schedule

Member for

22 years 6 months

Hi Mary



My response below :



Level 2 : This normally is a Project Integrated Schedule - which includes all work broken down into manageable packages, where responsibility, time, cost and resources are embedded in the detail and interfaces between the work packages and functions identified.(Typically 250-300 activities depending on project size of course!)



Best Regards

Andy