DESIGN OVERVIEW

Planning Application Approved

Scheme Design (GA’s for presentation to Client)

Issue GA’s to School Governors

Meet with School Governors

Agree Scheme Design

Finialise Scheme Design and Freeze

Detail Design

Client / User Group Consultation

Financial Close

Contractor Design



DESIGN DEVELOPMENT

Review Concept Design, Schedules & Accommodation - 1:200’s

Agree Concept Design with School

XXX XXX School agree Furniture and Equipment

1:200 Drawings Production/Completion/Amendment

Co-ordination of Engineering / Costs with Design Team

Review 1:200 Drawings with School Stakeholders

Finalise 1:200 Drawings inc Review Changes and Alterations

Issue Final 1:200 Drawings to School / Design Team

Detailed Design

Conctactor’s Proposals Document

Project Executation Plan



CONSTRUCTION WORKS

Site Logistics and Enablement Works

Set Up Site

Demolition and Site Clearance

Ground Remediation and Vibro-Compaction

Statutory Services and Road Diversions

Construct Road new Yyyy Way/Zzzz Roads etc

Re-route Gas Mains

Re-route Electricity Mains

Water Mains and Fire Hydrant Diversions

Sewer Diversion

Cable TV Diversions

Complete Final Fix, Signs, Lighting etc

Open New Roadway to Public

Works to Xxxx Lane Pavement and Trafic Islands

Make Good / Re-Surface Xxxx Lane incl Line Painting

AREA 1 - TEACHING BLOCK

Construct Column Bases & Underground Drainage

Incomming Services

Concrete Ground Slab

Erect Steel Columns and Beams

Pre-Cast Concrete Planks

Precast Concrete Staircases

Cladding to Atrium Canopy incl Scaffolding

Rebar / Underfloor Heating pipework / Insulation

Concrete and Power Float

Balustrading to Walkways and Staircases

Metsec Jumbo Stud/Insul/Bd to Partitions to Perimeters

Internal Dry Wall Partitions Board one side

Internal Blockwork

External Brickwork and Terra-Cotta Tiles

Doors, Windows, Roof Lights & Atrium Glazing

Roof Insulation and Membrane

External Render

Soil & Vent Stacks and Rainwater Goods

Electrical Installation

Mechanical Services Installation

Suspended Ceilings to corridor/offices

Carpentry and Joinery

Toilet Fit-Out

ICT / Communications Fit-Out

Internal Painting and Decorating

FloorFinishes

Fixtures Fittings & Equipment

Final Clean & Snag

AREA 2 -

Construct Column Bases & Underground Drainage

Incomming Services

Concrete Ground Slab

Erect Steel Columns and Beams

Pre-Cast Concrete Planks

Precast Concrete Staircases

Cladding to Atrium Canopy incl Scaffolding

Rebar / Underfloor Heating pipework / Insulation

Concrete and Power Float

Balustrading to Walkways and Staircases

Metsec Jumbo Stud/Insul/Bd to Partitions to Perimeters

Internal Dry Wall Partitions Board one side

Internal Blockwork

External Brickwork and Terra-Cotta Tiles

Doors, Windows, Roof Lights & Atrium Glazing

Roof Insulation and Membrane

External Render

Soil & Vent Stacks and Rainwater Goods

Electrical Installation

Mechanical Services Installation

Suspended Ceilings to corridor/offices

Carpentry and Joinery

Kitchen Fit-Out

ICT / Communications Fit-Out

Internal Painting and Decorating

FloorFinishes

Fixtures Fittings & Equipment

Final Clean & Snag

AREA 3 -

Construct Column Bases & Underground Drainage

Incomming Services

Concrete Ground Slab

Erect Steel Columns and Beams

Pre-Cast Concrete Planks

Precast Concrete Staircases

Cladding to Atrium Canopy incl Scaffolding

Rebar / Underfloor Heating pipework / Insulation

Concrete and Power Float

Balustrading to Walkways and Staircases

Metsec Jumbo Stud/Insul/Bd to Partitions to Perimeters

Internal Dry Wall Partitions Board one side

Internal Blockwork

External Brickwork and Terra-Cotta Tiles

Doors, Windows, Roof Lights & Atrium Glazing

Roof Insulation and Membrane

External Render

Soil & Vent Stacks and Rainwater Goods

Electrical Installation

Mechanical Services Installation

Suspended Ceilings to corridor/offices

Carpentry and Joinery

Toilet Fit-Out

Kitchen Fit-Out

ICT / Communications Fit-Out

Internal Painting and Decorating

FloorFinishes

Fixtures Fittings & Equipment

Final Clean & Snag





BUT PLEASE NOTE that you have to study the drawings for your project and work out what has to be done, and in what sequence, and with what resources. The drawings will have the answers when you have understood what you are about to build and when you have worked out how you are going to go about it.



GOOD LUCK

Daya

Member for

20 years 3 months

Hi David,



Please try the sample projects of planning software, Primavera P3, MS Project, Spider, etc. From these sample projects, visualize your construction sequence of making a school buildings.



You can do it. At the same time, you will develop "critical thinking" the hall mark of planners.



cheers,



charlie

Member for

20 years 2 months

I mean to say that since I have not P3 in my Laptop therefore I request all the information in Excel just to see sequence of activities such as



a)Design Finalization

b)Mobilization

c) Procurement

d)Construction Phase

Foundations

Structures

Roofing

Finishes (plumbing, Electrical and

Testing and Commisioning

Handing over



coz in UK, Foundation, Structures and Roofing for buildings and school is different as per location so I need some detailed activoites under these heads for Foundation, Structure and Roofing with 4~5 activities





Just wanna to get these only

Member for

20 years 5 months

In Excel ? Never heard.



What about starting with:

Basic design

Detail design

Procurement/manufacturing

Construction (Excavation/foundat.construct/etc)

Finishings

equipment

testing

handover to client



BR

JMFrade