what version of P6 are you using Also look at Plannex they have a free add in excel tool that you can paste info from P6 to Elxcel and then have it color the wbs and group the wbs based in teh p6 heicharcy.
I always do an Export first, creating my own template in Excel
Sometimes, if you make an Export with three 'sheets', Activities, Resources and Relationships, it is best to import each sheet separately. Not known why
Member for
16 years 3 monthsI have a few what are you
I have a few what are you looking for ?
what version of P6 are you using Also look at Plannex they have a free add in excel tool that you can paste info from P6 to Elxcel and then have it color the wbs and group the wbs based in teh p6 heicharcy.
Thsi tools also
Draws a Gantt chart
creates S curves
creates a XER with a wbs using excel
here is the link
https://plannexcg.com/plannex-tool/
Member for
9 years 8 monthsI always do an Export first,
I always do an Export first, creating my own template in Excel
Sometimes, if you make an Export with three 'sheets', Activities, Resources and Relationships, it is best to import each sheet separately. Not known why