go to the calculations tab and on the right make sure that on the right under resource assignments that recalculate actual units and costs when duration % complete changes
now go to the defaults tab there and under defaults for new activities that the percent complete type is set to duration
now when you update and activity lets say that is 10 days original duration and you progress it to 50% complete then the remaining duration will automaticaly be 5 days.
if you are using physcial % complete then go tot tools
Thank you for the reply. Been there, I have been on DOE jobs. I tend to keep it mixed, in particular with novices because the they will be working backwards into some items anyway such as procurement items and unfortunately it is simply easier to adjust the OD to let the computer do it. Earned Value is common on this site, but in general is not that commonly used in broad construction - mainly Federal government projects only, and even then mainly DOE and military.
Duration per cent complete is connected to the ratio of remaining duration to original duration, with the restriction that the value is always 0-100. For example, you could have an original duration of 10 days, and a remaining duration of 11 days, the duration % complete will be 0.
Duration % complete is not necessarily linked to Activity % complete, that depends on the Percent Complete type of the Activity. All expert uses of P6 require the Percent Complete type to be ‘Physical’ because that is the only way to do full Earned Value Analysis in P6.
Member for
16 years 3 monthsseveral ways herego to the
several ways here
go to the projects directory
highlight your project
go to the calculations tab and on the right make sure that on the right under resource assignments that recalculate actual units and costs when duration % complete changes
now go to the defaults tab there and under defaults for new activities that the percent complete type is set to duration
now when you update and activity lets say that is 10 days original duration and you progress it to 50% complete then the remaining duration will automaticaly be 5 days.
if you are using physcial % complete then go tot tools
gobal change
then New
If Parameter Is Value
Where physical % complete is not equal to 0
Then Parameter Is Value
duration % complte = Physcial % complete
then on the right select change
Member for
12 years 5 monthsThank you for the reply.
Thank you for the reply. Been there, I have been on DOE jobs. I tend to keep it mixed, in particular with novices because the they will be working backwards into some items anyway such as procurement items and unfortunately it is simply easier to adjust the OD to let the computer do it. Earned Value is common on this site, but in general is not that commonly used in broad construction - mainly Federal government projects only, and even then mainly DOE and military.
Member for
9 years 8 monthsDuration per cent complete is
Duration per cent complete is connected to the ratio of remaining duration to original duration, with the restriction that the value is always 0-100. For example, you could have an original duration of 10 days, and a remaining duration of 11 days, the duration % complete will be 0.
Duration % complete is not necessarily linked to Activity % complete, that depends on the Percent Complete type of the Activity. All expert uses of P6 require the Percent Complete type to be ‘Physical’ because that is the only way to do full Earned Value Analysis in P6.