If you use Fixed Units on Duration type, therefore duration will follow on Resources availability when assigning resources.
Ex: Duration Type: Fixed Units
% Complete Type: Duration
Calendar working hours : 12hrs/day
If the activity has 10days duration when assigning resources the resource will automatically populated as 120hrs. If the resource units change to 96hrs, the activity duration will automatically change to 8 days.
If you added a new resource, the activity duration will change based on Resource Assignment setting at User Preference -->Calculation tab --> Resource Assignments
When adding or removing multiple resource on activity:
- Preserve the unit, duration, and unit/time for existing assignments
- Recalculate the Unit, Duration and Unit/Time for existing assignments based on the activity Duration type
If Preserve is selected, the behaviour of duration and units will be the same as is and will not change
If Recalculate is selected, the behaviour of duration and units will be acording to duration type.
On your case, it seems that the Preserve is selected on your settings.
Member for
19 yearsHi Rod, No worries. Happy to
Hi Rod, No worries. Happy to help.
Member for
13 years 4 monthsRodel to the Rescue once
Rodel to the Rescue once again. Yes, I knew I was forgetting a switch somewhere. Thanks again Mate. All fixed and working as expected now.
Member for
13 years 4 monthsRodel to the Rescue once
Rodel to the Rescue once again. Yes, I knew I was forgetting a switch somewhere. Thanks again Mate. All fixed and working as expected now.
Member for
13 years 4 monthsRodel to the Rescue once
Rodel to the Rescue once again. Yes, I knew I was forgetting a switch somewhere. Thanks again Mate. All fixed and working as expected now.
Member for
13 years 4 monthsRodel to the Rescue once
Rodel to the Rescue once again. Yes, I knew I was forgetting a switch somewhere. Thanks again Mate. All fixed and working as expected now.
Member for
13 years 4 monthsRodel to the Rescue once
Rodel to the Rescue once again. Yes, I knew I was forgetting a switch somewhere. Thanks again Mate. All fixed and working as expected now.
Member for
13 years 4 monthsRodel to the Rescue once
Rodel to the Rescue once again. Yes, I knew I was forgetting a switch somewhere. Thanks again Mate. All fixed and working as expected now.
Member for
19 yearsHi Rod,If you use Fixed
Hi Rod,
If you use Fixed Units on Duration type, therefore duration will follow on Resources availability when assigning resources.
Ex: Duration Type: Fixed Units
% Complete Type: Duration
Calendar working hours : 12hrs/day
If the activity has 10days duration when assigning resources the resource will automatically populated as 120hrs. If the resource units change to 96hrs, the activity duration will automatically change to 8 days.
If you added a new resource, the activity duration will change based on Resource Assignment setting at User Preference -->Calculation tab --> Resource Assignments
When adding or removing multiple resource on activity:
- Preserve the unit, duration, and unit/time for existing assignments
- Recalculate the Unit, Duration and Unit/Time for existing assignments based on the activity Duration type
If Preserve is selected, the behaviour of duration and units will be the same as is and will not change
If Recalculate is selected, the behaviour of duration and units will be acording to duration type.
On your case, it seems that the Preserve is selected on your settings.