Primavera SDK - ODBC Problem (MS Access link)

Member for

19 years

Higher version of P6 is no longer supported by SDK, therefore if you upgraded your P6 version, your SDK will no longer working. The only option is connect it to ODBC using SQL server instead of Primavera SDK.

Member for

9 years 8 months

Marc,

 

You are entering a world of pain here. I don't know which of the 64 vs 32 bit issues you are tripping over, but you might not find a solution. If there was just one project, then exporting to Excel would be a suitable workaround. But as I am sure you are aware the Excel update is one project at a time. You might need to buy a third party anything-to-Primavera interface toolkits, like Legare.