Oracle Primavera - PM6 Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Thu, 2023-02-02 10:33 Permalink You can create a resources You can create a resources for that purpose and assign cost to all activities, factored by Weighting that you have per EPCC WBS Member for 9 years 8 months Member for 9 years 8 months Submitted by David Kelly on Wed, 2023-02-01 11:39 Permalink You could use the WBS You could use the WBS facility 'WBS Milestone % complete' in order to exactly track the EPCC percentages you quote. Log in or register to post comments
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Thu, 2023-02-02 10:33 Permalink You can create a resources You can create a resources for that purpose and assign cost to all activities, factored by Weighting that you have per EPCC WBS
Member for 9 years 8 months Member for 9 years 8 months Submitted by David Kelly on Wed, 2023-02-01 11:39 Permalink You could use the WBS You could use the WBS facility 'WBS Milestone % complete' in order to exactly track the EPCC percentages you quote.
Member for
19 yearsYou can create a resources
You can create a resources for that purpose and assign cost to all activities, factored by Weighting that you have per EPCC WBS
Member for
9 years 8 monthsYou could use the WBS
You could use the WBS facility 'WBS Milestone % complete' in order to exactly track the EPCC percentages you quote.