1) Any fields with * are calculated field and cannot be imported
2) There are 5 tables that can be updated using MS Excel such as:
a) Activity table (TASK)
b) Activity Relationships (TASKPRED)
c) Expenses (PROJCOST)
d) Resources (RSRC) - resource library
e) Resource Assignment (TASKRSRC)
Default columns per subject areaActivitiesActivity RelationshipsExpensesResourcesResource AssignmentsActivity IDPredecessorActivity IDResource IDActivity IDActivity StatusSuccessorExpense ItemResource NameActivity StatusWBS CodeRelationship TypeActivity StatusResource TypeResource IDActivity NamePredecessor Activity StatusBudgeted/Planned CostUnit of MeasureRole IDStartSuccessor Activity StatusActual CostRole IDCost Account IDFinishPredecessor ProjectRemaining CostDefault Units / TimeResource TypeResourcesSuccessor ProjectAt Completion Cost Price / Unit Predecessor WBS Start Successor WBS Finish Predecessor Activity Name Successor Activity Name Lag Predecessor Primary Resource Successor Primary Resource
Note:
Italic text indicates that the column is required for importing and exporting. The column cannot be removed from the export template and must exist in the import file to import successfully.
Member for
20 years 6 monthsAlso remember, if you
Also remember, if you generate an XLS Export from P6, the columns marked with an (*) cannot be imported in.
Member for
19 yearsBasic Importing Note P6 using
Basic Importing Note P6 using MS Excel
1) Any fields with * are calculated field and cannot be imported
2) There are 5 tables that can be updated using MS Excel such as:
a) Activity table (TASK)
b) Activity Relationships (TASKPRED)
c) Expenses (PROJCOST)
d) Resources (RSRC) - resource library
e) Resource Assignment (TASKRSRC)
Default columns per subject area ActivitiesActivity RelationshipsExpensesResourcesResource AssignmentsActivity IDPredecessorActivity IDResource IDActivity IDActivity StatusSuccessorExpense ItemResource NameActivity StatusWBS CodeRelationship TypeActivity StatusResource TypeResource IDActivity NamePredecessor Activity StatusBudgeted/Planned CostUnit of MeasureRole IDStartSuccessor Activity StatusActual CostRole IDCost Account IDFinishPredecessor ProjectRemaining CostDefault Units / TimeResource TypeResourcesSuccessor ProjectAt Completion Cost Price / Unit Predecessor WBS Start Successor WBS Finish Predecessor Activity Name Successor Activity Name Lag Predecessor Primary Resource Successor Primary Resource
Note:
Italic text indicates that the column is required for importing and exporting. The column cannot be removed from the export template and must exist in the import file to import successfully.