ETC different than Budgeted labour units for not started activity

Member for

19 years

Hi Hamza,

The estimated quantity to complete the activity. Computed as either the remaining total units for the activity, or as Performance Factor * (Baseline Budgeted Labor Units - Budgeted Quantity of Work Performed), depending on the Earned Value Technique selected for the activity's WBS such as:

Activity-Earned-Value

Member for

5 years 9 months

Hello Rodel Marasigan,

Yes it seems like the Project Baseline has different budgeted units than the current project which brings me to my question: Why does P6 takes into account Project Baseline when calculating current project ETC labour units?

Member for

19 years

It seems that the Baseline had different Budgeted Unit compare to your current schedule. To confirm, restore the baseline and check the activity that showing different Budgeted Unit and ETC if still the same.