Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2023-01-13 15:34 Permalink also in version 22.4 there is also in version 22.4 there is a tool in P6 its under view then check schedule its a list like the DCMA 14 point also look for a utility called xer reader it uses an xer file and performs the 14 point for you Member for 20 years 5 months Member for 20 years 5 months Submitted by Peter Holroyd on Sat, 2022-12-17 11:02 Permalink There's loads of P6 add ons There's loads of P6 add ons that have this covered. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2023-01-13 15:34 Permalink also in version 22.4 there is also in version 22.4 there is a tool in P6 its under view then check schedule its a list like the DCMA 14 point also look for a utility called xer reader it uses an xer file and performs the 14 point for you
Member for 20 years 5 months Member for 20 years 5 months Submitted by Peter Holroyd on Sat, 2022-12-17 11:02 Permalink There's loads of P6 add ons There's loads of P6 add ons that have this covered.
Member for
16 years 3 monthsalso in version 22.4 there is
also in version 22.4 there is a tool in P6 its under view then check schedule its a list like the DCMA 14 point
also look for a utility called xer reader it uses an xer file and performs the 14 point for you
Member for
20 years 5 monthsThere's loads of P6 add ons
There's loads of P6 add ons that have this covered.