Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2022-10-18 14:57 Permalink yes use dissolve so you do yes use dissolve so you do not have an activity without a predcessor or successor A fs to B and B fs to C A--->B--->C if you dissolve B then A will tie to C A--->C Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2022-10-18 14:57 Permalink yes use dissolve so you do yes use dissolve so you do not have an activity without a predcessor or successor A fs to B and B fs to C A--->B--->C if you dissolve B then A will tie to C A--->C
Member for
16 years 3 monthsyes use dissolve so you do
yes use dissolve so you do not have an activity without a predcessor or successor
A fs to B and B fs to C
A--->B--->C
if you dissolve B then A will tie to C
A--->C