Why can't I open two projects and copy activities from one to the other? pastes into the same...

Member for

12 years 5 months

Wow, fastest answer ever on this site.  Thank you very much.

Member for

12 years 5 months

Wow, fastest answer ever on this site.  Thank you very much.

Member for

9 years 8 months

Yes there is a trick. Some of this might not be necessary now, but I always:

Group and sort by WBS
Do not 'hide if empty'
Always select using the left mouse button, before right-clicking and paste