Performance % Complete

Member for

19 years

The activity performance percent complete is used to compute earned value and may be based on the Activity % Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of the activity's planned worth has been earned so far.

You can set the performance percent complete under WBS module. See below:

Performance-percent-Complete

Member for

16 years 3 months

Tools

Admin Preferences

Earned Value Tab

Make sure that the Technique for computing performance percent complete is set to

Activity % Complete

and that Earned value calculation is set to Budgeted Values with current date is at the bottom of this same tab.

Also at the Project levele under Setings make sure that Baseline for earned value calculatons is  set to Project Baseline

Member for

9 years 8 months

It is at the WBS level, the Earned Value tab.