the PP forum tools are quite outdated and can't handle images attached into the posts. Another option you have is to save you image as a JPG/PNG file on your PC, then use an image hosting provider to upload, then refernce the image in your post.
For example, you can go to Imgur: The magic of the Internetand you don't need to register or anything, just hit "New Post" and then load the file. You will then see a button for share links and you copy the HTML link and then just paste that here into the PP post.
Zoltans example
Given that we can't see the image, it may be one of the following
1) Split activities
2) Multiple bar styles, P6 positions bars in an order in the Bars lists, so one bar with one colour, might be sitting just above, or below another bar showing the same activity as a different colour. However I'd be surprised if its this as they should all be showing the same dates
3) Roll up of a group where the bars are being shown when grouped.
OK, I tried to post graphics and they didn't show up. Let mw know how to post graphics perhaps but I will describe it...His bars are green except for the ends are red with just the critical days remaining on each. When I do it, the entire bar is red.
Member for
16 years 3 monthscan you please reference the
can you please reference the post and I can tell you how i did it
Member for
20 years 6 monthsJohn,Posting Imagesthe PP
John,
Posting Images
the PP forum tools are quite outdated and can't handle images attached into the posts. Another option you have is to save you image as a JPG/PNG file on your PC, then use an image hosting provider to upload, then refernce the image in your post.
For example, you can go to Imgur: The magic of the Internetand you don't need to register or anything, just hit "New Post" and then load the file. You will then see a button for share links and you copy the HTML link and then just paste that here into the PP post.
Zoltans example
Given that we can't see the image, it may be one of the following
1) Split activities
2) Multiple bar styles, P6 positions bars in an order in the Bars lists, so one bar with one colour, might be sitting just above, or below another bar showing the same activity as a different colour. However I'd be surprised if its this as they should all be showing the same dates
3) Roll up of a group where the bars are being shown when grouped.
Member for
12 years 5 monthsOK, I tried to post graphics
OK, I tried to post graphics and they didn't show up. Let mw know how to post graphics perhaps but I will describe it...His bars are green except for the ends are red with just the critical days remaining on each. When I do it, the entire bar is red.