Activity Code Description values rather than Code Value in Exporting Data

Member for

16 years 3 months

glad I could help you 

Member for

7 years 10 months

I have V20 and was able to change the option in user preferences to description. thanks

Member for

19 years

The code Description values option in User Preference --> Application tab is only available in P6 r20 up. Not available on lower version of P6.

Member for

16 years 3 months

go to edit user preferences click on the Application lab

then under the Codes section under Specify how to display code values

select Description instead of Code Value

now get it how you want it in the tabular area then copy and paste to excel

you can also create a UDF which is user defined field and make it a text value and import these back into P6

then you will have them