Resource Leveling

Member for

19 years

Hamid,

Make sure that no overallocated on each activities as it will not move because it is already overallocated. Overlaping activities is fine as long as it will be level accordingly. Make sure the maximum limit is set ex: say 5 res x 8hrs/day = 40hrs/day

Member for

12 years 2 months

Hi Rodel,
 
If an activity itself is over-allocated, the duration will not change after leveling to resolve the overallocation?
I defined a small project for better monitoring. Even in overlapping activities, when I run level resources (Considering the 3 items you mentioned earlier), no change occurs. is there any special adjustment needed before leveling that may I have forgotten?

Member for

19 years

Hi Hamid,

As you mentioned, your setting is Fixed Units. Is the activity itself is over allocated? It so then overallocated resource on activities will not move or will not level.

Member for

12 years 2 months

Hi Rodel,

I selected “Preserve scheduled early and late dates” and some change has happened, but still, I am faced with over-allocated resources in some parts.

Member for

12 years 2 months

Hi Rodel,

I selected “Preserve scheduled early and late dates” and some change has happened, but still, I am faced with over-allocated resources in some parts.

Member for

19 years

Hi Hamid,

When you run Level Resource (shift+F9). Did you select:

1. Automatically Level Resources when scheduling

2. Preserve schedule early and late dates

3. Level all resources

Also did you select the field names you use for levelling priorities?