Make sure that no overallocated on each activities as it will not move because it is already overallocated. Overlaping activities is fine as long as it will be level accordingly. Make sure the maximum limit is set ex: say 5 res x 8hrs/day = 40hrs/day
Member for
12 years 2 months
Member for12 years2 months
Submitted by Hamid Tavassoli on Sun, 2022-02-13 16:37
If an activity itself is over-allocated, the duration will not change after leveling to resolve the overallocation?
I defined a small project for better monitoring. Even in overlapping activities, when I run level resources (Considering the 3 items you mentioned earlier), no change occurs. is there any special adjustment needed before leveling that may I have forgotten?
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Sun, 2022-02-13 11:38
As you mentioned, your setting is Fixed Units. Is the activity itself is over allocated? It so then overallocated resource on activities will not move or will not level.
Member for
12 years 2 months
Member for12 years2 months
Submitted by Hamid Tavassoli on Sun, 2022-02-13 10:32
Member for
12 years 2 monthsRodel,Thank you very much for
Rodel,
Member for
12 years 2 monthsRodel,Thank you very much for
Rodel,
Member for
19 yearsHamid,Make sure that no
Hamid,
Make sure that no overallocated on each activities as it will not move because it is already overallocated. Overlaping activities is fine as long as it will be level accordingly. Make sure the maximum limit is set ex: say 5 res x 8hrs/day = 40hrs/day
Member for
12 years 2 monthsHi Rodel, If an activity
Member for
19 yearsHi Hamid,As you mentioned,
Hi Hamid,
As you mentioned, your setting is Fixed Units. Is the activity itself is over allocated? It so then overallocated resource on activities will not move or will not level.
Member for
12 years 2 monthsHi Rodel,I selected “Preserve
Hi Rodel,
I selected “Preserve scheduled early and late dates” and some change has happened, but still, I am faced with over-allocated resources in some parts.
Member for
12 years 2 monthsHi Rodel,I selected “Preserve
Hi Rodel,
I selected “Preserve scheduled early and late dates” and some change has happened, but still, I am faced with over-allocated resources in some parts.
Member for
19 yearsHi Hamid,When you run Level
Hi Hamid,
When you run Level Resource (shift+F9). Did you select:
1. Automatically Level Resources when scheduling
2. Preserve schedule early and late dates
3. Level all resources
Also did you select the field names you use for levelling priorities?