Is resource referencing superior to resource loading? I find it to be much faster and useful...did I invent that term?

Member for

21 years 8 months

For Volumes of Work and Productivities be considered in Monte Carlo as non-deterministic parameters activity durations must be driven by non-deterministic resource/crew production rates and resources must be leveled on each iteration. 

2022-01-29-23-32-42



2022-01-29-23-33-34

It can be argued that it is assignments productivity the parameter that best define the correlation among activities.

MC-Correlations

 

Member for

19 years

Resource referencing is only for information purposes and cannot be used for reporting, analysis and other meaningful functioned of resource loading. You cannot do resource leveling in resource referencing. You cannot prepare S-Curve and other meaningful report. You cannot do risk performance and analysis...etc.