You cannot use P6 import/export function in excel to create a WBS dictionary into P6 Project. The best way is to use the excel XER parser & builder. You can create a WBS dictionary for a project using this tools. But you need to learn how to use it first. See link for your reference. How to Import WBS using excel XER parser
Member for
7 years 7 monthsSee this amazing tool to
https://www.youtube.com/playlist?list=PLFPaRgp0OMtk3Fl88xFKiQjpBD4CnLm0U
Member for
19 yearsHi Steven,You cannot use P6
Hi Steven,
You cannot use P6 import/export function in excel to create a WBS dictionary into P6 Project. The best way is to use the excel XER parser & builder. You can create a WBS dictionary for a project using this tools. But you need to learn how to use it first. See link for your reference. How to Import WBS using excel XER parser