On Same Data Date Actual Units Doesn't Equal Cum AtCompletion Units

Member for

16 years 3 months

that will do it

Member for

5 years 10 months

I found the problem. Some acitivities in progress have 0-zero- Rem duration. This causes a problem.

Member for

5 years 10 months

I found the problem. Some acitivities in progress have 0-zero- Rem duration. This causes a problem.