How to modify "Note to ressource" field

Member for

16 years 3 months

Clear the checkbox when you finish reading the new feedback so you will be aware of subsequent new feedback.

Member for

19 years 7 months

Hi,

in fact I can't find any parameter in admin part. If anybody have a clue to find it, it would nice

Member for

16 years 3 months

check your admin rights and make sure you have the proper rights to do this.

Member for

22 years 9 months

Hello Frederic,

"Note to resource" allows the planner to write/send short notices to the ressources assigned to this specific activity. the resource then will be able to answer in the right side of the screen. This build some kind of forum where the planner and the resource will discuss the data pertaining to the activity.

In my own opinion, it is more coherent not to be able to delete or edit the notes, in order to keep the forum history alive.

Alexandre