Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2021-04-13 14:13 Permalink it may well be ahead of the it may well be ahead of the planned or baseline schedule Member for 20 years 6 months Member for 20 years 6 months Submitted by Santosh Bhat on Tue, 2021-04-13 02:56 Permalink You have retained logic You have retained logic running through the predecessors of that task, check the relationships have been upheld as you've enterered the actual dates. Member for 21 years 9 months Member for 21 years 9 months Submitted by Jerome Odeh on Mon, 2021-04-12 15:32 Permalink Hi Zoltan,Won't changing Hi Zoltan, Won't changing Actual Work setting to Current Bar make it show progress beyond data date? Jerome Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2021-04-12 15:16 Permalink here is the fix go to bars go here is the fix go to bars go to the actual work bar and in the 3rd column (time scale) chneg this setting from Actual bar to Current bar Member for 21 years 9 months Member for 21 years 9 months Submitted by Jerome Odeh on Sat, 2021-04-10 15:25 Permalink Moutaz,Most likely the your Moutaz, Most likely the your calendar start time is 08:00 while your data date time is 00:00 Check this blog post for details https://www.plannersplace.com/blog/how-remove-gaps-after-data-date-primavera-p6 =jerome Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2021-04-13 14:13 Permalink it may well be ahead of the it may well be ahead of the planned or baseline schedule
Member for 20 years 6 months Member for 20 years 6 months Submitted by Santosh Bhat on Tue, 2021-04-13 02:56 Permalink You have retained logic You have retained logic running through the predecessors of that task, check the relationships have been upheld as you've enterered the actual dates.
Member for 21 years 9 months Member for 21 years 9 months Submitted by Jerome Odeh on Mon, 2021-04-12 15:32 Permalink Hi Zoltan,Won't changing Hi Zoltan, Won't changing Actual Work setting to Current Bar make it show progress beyond data date? Jerome
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2021-04-12 15:16 Permalink here is the fix go to bars go here is the fix go to bars go to the actual work bar and in the 3rd column (time scale) chneg this setting from Actual bar to Current bar
Member for 21 years 9 months Member for 21 years 9 months Submitted by Jerome Odeh on Sat, 2021-04-10 15:25 Permalink Moutaz,Most likely the your Moutaz, Most likely the your calendar start time is 08:00 while your data date time is 00:00 Check this blog post for details https://www.plannersplace.com/blog/how-remove-gaps-after-data-date-primavera-p6 =jerome
Member for
16 years 3 monthsit may well be ahead of the
it may well be ahead of the planned or baseline schedule
Member for
20 years 6 monthsYou have retained logic
You have retained logic running through the predecessors of that task, check the relationships have been upheld as you've enterered the actual dates.
Member for
21 years 9 monthsHi Zoltan,Won't changing
Hi Zoltan,
Won't changing Actual Work setting to Current Bar make it show progress beyond data date?
Jerome
Member for
16 years 3 monthshere is the fix go to bars go
here is the fix go to bars
go to the actual work bar and in the 3rd column (time scale) chneg this setting from Actual bar to Current bar
Member for
21 years 9 monthsMoutaz,Most likely the your
Moutaz,
Most likely the your calendar start time is 08:00 while your data date time is 00:00
Check this blog post for details
https://www.plannersplace.com/blog/how-remove-gaps-after-data-date-primavera-p6
=jerome