Zoltan - Absolutely, I was hoping to save myself a minor amount of effort.
Santosh - I am not sure, but you are likely correct as I used EPPM sparingly previously (years ago) and probably for this reason. I don't have EPPM capabilities currently.
Thank you both.
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Fri, 2021-02-26 15:47
Casey, I might be wrong, but thats a feature only available in P6 EPPM using the Web - P6 PPM using the traditional client has never had a formula feature for UDF's.
Member for
9 years 5 monthsZoltan - Absolutely, I was
Zoltan - Absolutely, I was hoping to save myself a minor amount of effort.
Santosh - I am not sure, but you are likely correct as I used EPPM sparingly previously (years ago) and probably for this reason. I don't have EPPM capabilities currently.
Thank you both.
Member for
16 years 3 monthsI am not sure that I
I am not sure that I understand the question you can run a global change and do the math there to get the UDF value that you want.
Member for
20 years 6 monthsCasey, I might be wrong, but
Casey, I might be wrong, but thats a feature only available in P6 EPPM using the Web - P6 PPM using the traditional client has never had a formula feature for UDF's.