Activity Name Fields Are Sometimes Missing In Printed PDF

Member for

12 years 11 months

haha yes. same issue.

Member for

16 years 3 months

have you re-booted the computer ?

Member for

12 years 11 months

"Yield=On" is already present in the PM.INI file.

But the error still persists.

Member for

16 years 3 months

The issue is caused by a missing setting in the PM.ini file.

SOLUTION

Edit the user's PM.ini file to add "Yield=ON" under [Printer Options] and save the file. After the user logs out and back in again, the change will be reflected.

The location of the PM.ini file may be in the default location (ex. C:\Program Files\Oracle\Primavera P6\P6 Professional\PM.ini) or in a user's "home" folder (ex. C:\Users\<User Name>\AppData\Local\Oracle\Primavera P6\P6 Professional\).