it probally has to do with your TIMES and durations
go to edit users preferences and select the time units tab then look at the durations format make sure that the Decimal places is set to 2.
then go to the dates tab there and at the bottom select TIME :12:00 (1:30 PM) and select show miniutes.
what happens here is that lets say that an activity has a 5 day duration and you progress this to 50% thsi will make the remaining duration 2.5 days This means that the activity will end in the middll or at 12:00 noon of the 3rd day. That means that any successor can begin at noon on that same day. You can clearly see this for a 1 day activity that actually spans 2 days.
1. make all of you reamining durations whole numbers
2. make any actual start date TIMES 8:00 AM
3. Make any actual finish dates TIMES 17:00 PM
4. Make any start constraint date times 8:00 AM
5. Make any finish constraint date times 17:00 PM
6. Make the project START DATE TIME to 8:00 AM
7. Make the project must finish by date time: 17:00 PM
8. Change the data date time to 8:00 AM
That should fix it also make sure that your activities are assigned to the correct calendar
Member for
21 years 8 months
Member for21 years8 months
Submitted by Rafael Davila on Mon, 2021-02-08 03:40
Follow the steps on my article linked below to troubleshoot your issue, it will be either due to durations or due to an issue with the calendar you're using:
Member for
16 years 3 monthsit probally has to do with
it probally has to do with your TIMES and durations
go to edit users preferences and select the time units tab then look at the durations format make sure that the Decimal places is set to 2.
then go to the dates tab there and at the bottom select TIME :12:00 (1:30 PM) and select show miniutes.
what happens here is that lets say that an activity has a 5 day duration and you progress this to 50% thsi will make the remaining duration 2.5 days This means that the activity will end in the middll or at 12:00 noon of the 3rd day. That means that any successor can begin at noon on that same day. You can clearly see this for a 1 day activity that actually spans 2 days.
1. make all of you reamining durations whole numbers
2. make any actual start date TIMES 8:00 AM
3. Make any actual finish dates TIMES 17:00 PM
4. Make any start constraint date times 8:00 AM
5. Make any finish constraint date times 17:00 PM
6. Make the project START DATE TIME to 8:00 AM
7. Make the project must finish by date time: 17:00 PM
8. Change the data date time to 8:00 AM
That should fix it also make sure that your activities are assigned to the correct calendar
Member for
21 years 8 monthsThe Inner Workings of P6It
The Inner Workings of P6
It gets better when different days of the week have different number of work hours for a given calendar, get used to it.
Member for
20 years 6 monthsMoutaz,Follow the steps on my
Moutaz,
Follow the steps on my article linked below to troubleshoot your issue, it will be either due to durations or due to an issue with the calendar you're using:
P6 Schedules - Activity Date / Time Issues | LinkedIn