of you use a a LOE type of activity then you MUST assign a resouce curve to that LOW activity or all of the resources wil stack up on the data date.

fro the LOE activity click onthe resource tab at the bottm 

then rigth click and select customize resource columns

expand the general category and select curve

then click in the curve box and select a curve teh standard curve is Linear

done