Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2020-12-23 14:04 Permalink if it has a variance it must if it has a variance it must be comparing against something do you have a baseline attached ? see if there is an actual cost or a cost to complete ? if there are values here it will still show a variance look at previous period costs Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2020-12-23 14:04 Permalink if it has a variance it must if it has a variance it must be comparing against something do you have a baseline attached ? see if there is an actual cost or a cost to complete ? if there are values here it will still show a variance look at previous period costs
Member for
16 years 3 monthsif it has a variance it must
if it has a variance it must be comparing against something do you have a baseline attached ?
see if there is an actual cost or a cost to complete ?
if there are values here it will still show a variance
look at previous period costs