One Day Filter

Member for

16 years 3 months

glad I could help 

Member for

16 years 3 months

you did not say if Dec 1 was the data date or a date in the future so 

filter 

where 

Activity status is not equal to complete

or 

Start is less than or equal to Dec 1

or 

Finish equals Dec 1

 

Member for

20 years 6 months

Heather, that wont capture activities that have started before 1st December and are currently in progress.

There are four scenarios that can happen on that day:

  • 1: Started before 1-Dec and will finish after 1-Dec. ie. in progress
  • 2: Started before 1-Dec, but will finish on 1-Dec
  • 3: Starts on 1-Dec and will finish after 1-Dec
  • 4: Starts and Finishes on 1-Dec

Your filters will need to be (OR) for all the above scenarios.