Remember up to four types of relationships can be added between two activities, and an Excel import in P6 is always to update the project file. So we have to follow the steps below:
Export out the .XLS file from P6 with the activity relationship tab.
In the activity relationship tab, filter only activities that you want to change FS to FF. Delete the other activity rows.
Copy all the relevant activity rows and paste below.
Go back the first set of relevant activity rows and in the delete tab type "d".
Go back to copied set of relevant activity and change activity relationships from FS to SS.
Save and close .XLS file.
Import into P6 and F9 to verify and check relationship tab in Activity Details.
Member for
16 years 3 monthsglad it worked for you
glad it worked for you
Member for
16 years 3 monthsglad it worked for you
glad it worked for you
Member for
12 years 7 monthsBian, Thank you very much. It
Bian, Thank you very much. It works.
Member for
11 years 4 monthsHi Irfan,Remember up to four
Hi Irfan,
Remember up to four types of relationships can be added between two activities, and an Excel import in P6 is always to update the project file. So we have to follow the steps below:
Please refer to the following video demo https://imgur.com/u0Pezy8