Oracle Primavera - PM6 Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Thu, 2020-10-22 08:56 Permalink Hi Jithin,you can create a Hi Jithin, you can create a new bar in wich you will assign a filter based on the "Variance BL1 Start Date", or "Variance BL1 Finish Date", or both Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Thu, 2020-10-22 08:56 Permalink Hi Jithin,you can create a Hi Jithin, you can create a new bar in wich you will assign a filter based on the "Variance BL1 Start Date", or "Variance BL1 Finish Date", or both Alexandre
Member for
22 years 9 monthsHi Jithin,you can create a
Hi Jithin,
you can create a new bar in wich you will assign a filter based on the "Variance BL1 Start Date", or "Variance BL1 Finish Date", or both
Alexandre