Export of Baseline

Member for

14 years 7 months

Hi Alex,

 

Ya its working. I exported a XML File and the baseline was in it.

Thanks for the tip.

 

Regards

Jithin

Member for

22 years 9 months

Hi Jithin,

are you working stand-alone, or client-server? in this case, is it possible that you are not allowed to export baselines?

I am using P6 stand-alone with a SQLite database, and exporting/re-importing the baselines works perfectly with the XML format

Alexandre

Member for

20 years 6 months

Alexandre,

Yes you are corect. Sorry, its been a long time since I've had to use the XML format.

Member for

14 years 7 months

Hi Alex,

 

I did export in XML Format, but again its not exporting the baseline.

 

And while exporting its asking if to include baseline and I have selected the baseline to be exported. But after exporting the and importing it to another machine I am not able to see the exported Baseline.

 

Is it a settings issue of Exporting Machine or Importing Machine ?

 

Thanks 

Jithin

Member for

22 years 9 months

Hi,

Santosh, it is possible to export baselines together with the current project in the xml export process; you may select the baseline you want to export

I guess this option exists since P6 17.x at the latest.

Alexandre

Member for

20 years 6 months

Baselines are not exported to those formats, you need to go MAINTAIN BASELINES>RESTORE BASELINES then export this restored project seperately. Remembe to then re-attach the baseline to the original project.