I did export in XML Format, but again its not exporting the baseline.
And while exporting its asking if to include baseline and I have selected the baseline to be exported. But after exporting the and importing it to another machine I am not able to see the exported Baseline.
Is it a settings issue of Exporting Machine or Importing Machine ?
Thanks
Jithin
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Tue, 2020-10-20 10:15
Santosh, it is possible to export baselines together with the current project in the xml export process; you may select the baseline you want to export
I guess this option exists since P6 17.x at the latest.
Alexandre
Member for
20 years 6 months
Member for20 years6 months
Submitted by Santosh Bhat on Tue, 2020-10-20 05:31
Baselines are not exported to those formats, you need to go MAINTAIN BASELINES>RESTORE BASELINES then export this restored project seperately. Remembe to then re-attach the baseline to the original project.
Member for
14 years 7 monthsHi Alex, Ya its working. I
Hi Alex,
Ya its working. I exported a XML File and the baseline was in it.
Thanks for the tip.
Regards
Jithin
Member for
22 years 9 monthsHi Jithin,are you working
Hi Jithin,
are you working stand-alone, or client-server? in this case, is it possible that you are not allowed to export baselines?
I am using P6 stand-alone with a SQLite database, and exporting/re-importing the baselines works perfectly with the XML format
Alexandre
Member for
20 years 6 monthsAlexandre,Yes you are corect.
Alexandre,
Yes you are corect. Sorry, its been a long time since I've had to use the XML format.
Member for
14 years 7 monthsHi Alex, I did export in XML
Hi Alex,
I did export in XML Format, but again its not exporting the baseline.
And while exporting its asking if to include baseline and I have selected the baseline to be exported. But after exporting the and importing it to another machine I am not able to see the exported Baseline.
Is it a settings issue of Exporting Machine or Importing Machine ?
Thanks
Jithin
Member for
22 years 9 monthsHi,Santosh, it is possible to
Hi,
Santosh, it is possible to export baselines together with the current project in the xml export process; you may select the baseline you want to export
I guess this option exists since P6 17.x at the latest.
Alexandre
Member for
20 years 6 monthsBaselines are not exported to
Baselines are not exported to those formats, you need to go MAINTAIN BASELINES>RESTORE BASELINES then export this restored project seperately. Remembe to then re-attach the baseline to the original project.