Insert the Planned Start and Planned Finish dates in the gantt chart columns; you should find that these dates are different from Early Start / Finish dates, and the same as Baseline ones.
When a project has no baseline, planned dates are used instead.
Years ago, the P6 guru Ron Winter had published a very interesting paper "Understanding P6 dates"; easy to find on the Internet, as I do not know how to share my local file on the forum
Member for
12 years 8 monthsThank you very much
Thank you very much Alexandre.
Member for
22 years 9 monthsHi Irfan,Insert the Planned
Hi Irfan,
Insert the Planned Start and Planned Finish dates in the gantt chart columns; you should find that these dates are different from Early Start / Finish dates, and the same as Baseline ones.
When a project has no baseline, planned dates are used instead.
Years ago, the P6 guru Ron Winter had published a very interesting paper "Understanding P6 dates"; easy to find on the Internet, as I do not know how to share my local file on the forum
Alexandre