Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2020-09-30 12:59 Permalink go to edit users go to edit users preference click on the time units tab under Unit of time make sure it says hour under durations format change that to hour then on the right under decimals make sure that is set to 2 decimals Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Wed, 2020-09-30 10:07 Permalink Hello,I am not sure to fully Hello, I am not sure to fully understand your question; P6 cannot display duration or work in minutes, the shorter unit being hours. When you enter "0.50h", i.e. "30 minutes", P6 displays the duration in the unit designed in User preferences. May I ask you another question? Is P6 the most appropriate planning software for such shorts tasks in a project? Alexandre Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2020-09-30 12:59 Permalink go to edit users go to edit users preference click on the time units tab under Unit of time make sure it says hour under durations format change that to hour then on the right under decimals make sure that is set to 2 decimals
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Wed, 2020-09-30 10:07 Permalink Hello,I am not sure to fully Hello, I am not sure to fully understand your question; P6 cannot display duration or work in minutes, the shorter unit being hours. When you enter "0.50h", i.e. "30 minutes", P6 displays the duration in the unit designed in User preferences. May I ask you another question? Is P6 the most appropriate planning software for such shorts tasks in a project? Alexandre
Member for
16 years 3 monthsgo to edit users
go to edit users preference
click on the time units tab
under Unit of time make sure it says hour
under durations format change that to hour
then on the right under decimals make sure that is set to 2 decimals
Member for
22 years 9 monthsHello,I am not sure to fully
Hello,
I am not sure to fully understand your question; P6 cannot display duration or work in minutes, the shorter unit being hours.
When you enter "0.50h", i.e. "30 minutes", P6 displays the duration in the unit designed in User preferences.
May I ask you another question? Is P6 the most appropriate planning software for such shorts tasks in a project?
Alexandre