is to NOT print the Gannt chat only print the tabular data this gives you more room to make the predcessor colums larger so that the wrapping does not make the row too large.
then give a seperate gantt chart without the prdcessor and successor columns
work around #2
is to give the client the predcessor report in excel
then give a seperate gantt chart without the prdcessor and successor columns
work around #3
give the client the detailed predcessor report from with in p6
then give a seperate gantt chart without the predcessor and successor columns
if you do not have this report I can give it to you can you can import the report its is a .erp file which you can import in the the reports area.
Member for
20 years 6 months
Member for20 years6 months
Submitted by Santosh Bhat on Fri, 2020-09-11 01:13
The reason the activity lines are so "tall" that the list of successors and predecessors get wrapped within the column width you provide and therefore increase the line height to fit this list. If you increase the width of these columns then the line height will reduce, but obviously means less space for the other content.
I think perhaps a conversation with the client will help in this instance. Advise them that the printed output size would be significantly reduced if the relationships weren't listed. Suggest you'll display relationships on the Gantt charts, and you're probably already providing an electronic copy of the schedule if they wish to investigate the relationships.
Member for
16 years 3 monthsgive me your email address
give me your email address and I will send it
Member for
11 years 4 monthsThanks for your response
Thanks for your response Zoltan and Santosh. I will adopt all your suggestions to present a report to the Client.
Zoltan, I would really like to have the .erp report you mentioned. Thanks in advance.
Member for
16 years 3 monthsSantioh is correctwork around
Santioh is correct
work around #1
is to NOT print the Gannt chat only print the tabular data this gives you more room to make the predcessor colums larger so that the wrapping does not make the row too large.
then give a seperate gantt chart without the prdcessor and successor columns
work around #2
is to give the client the predcessor report in excel
then give a seperate gantt chart without the prdcessor and successor columns
work around #3
give the client the detailed predcessor report from with in p6
then give a seperate gantt chart without the predcessor and successor columns
if you do not have this report I can give it to you can you can import the report its is a .erp file which you can import in the the reports area.
Member for
20 years 6 monthsRichard, The reason the
Richard,
The reason the activity lines are so "tall" that the list of successors and predecessors get wrapped within the column width you provide and therefore increase the line height to fit this list. If you increase the width of these columns then the line height will reduce, but obviously means less space for the other content.
I think perhaps a conversation with the client will help in this instance. Advise them that the printed output size would be significantly reduced if the relationships weren't listed. Suggest you'll display relationships on the Gantt charts, and you're probably already providing an electronic copy of the schedule if they wish to investigate the relationships.