It will use the earliest actual start date of any activites under that wbs and the latest finish (not late finish date) date for the activities under that wbs.
so if you update the schedule and things move to the right then the wbs summary will move to the right.
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Wed, 2020-09-09 09:20
Member for
16 years 3 monthsit is doing what its is
it is doing what its is supposed to do.
It summarizes ALL activities under that WBS.
It will use the earliest actual start date of any activites under that wbs and the latest finish (not late finish date) date for the activities under that wbs.
so if you update the schedule and things move to the right then the wbs summary will move to the right.
Member for
22 years 9 monthsHi Nathan,Please check that
Hi Nathan,
Please check that the bar for the wbs summary activities is not displaying the remaining duration only, but also the actual duration.
Alexandre