As I noted earlier, just the Global privilege is not enough. You also need to be assiged as Project SuperUser in the project profile of the REsponsible Manager for that project.
Member for
16 years 7 months
Member for16 years7 months
Submitted by Athar Hashmi on Thu, 2020-09-03 08:17
Hi Zoltan, under the secuirty profile -> Global profile -> Import .xls is checked, while in main import screen it gives the option to select spreadsheet with ".xlsx" extension. So there is conflict between the file extensions.
I have saved the file with .xls then imported it. In this case p6 is not recognising the file and all the option to import activities or resources, etc were disabled.
Conflict of file extension might be a reason?
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Tue, 2020-09-01 14:51
It has to do with the database security privileges for you. To import XLSS files you need both the Global privilege to import (which you must have as you get this far), and also be a Project Super User as the project security profile assigned to the responsible manager of that project.
You'll need to contact whimever administers the users in the P6 database you're working in to sort it out.
Member for
16 years 3 monthsSantosh is correct
Santosh is correct
Member for
20 years 6 monthsAs I noted earlier, just the
As I noted earlier, just the Global privilege is not enough. You also need to be assiged as Project SuperUser in the project profile of the REsponsible Manager for that project.
Member for
16 years 7 monthsHi Zoltan, under the secuirty
Hi Zoltan, under the secuirty profile -> Global profile -> Import .xls is checked, while in main import screen it gives the option to select spreadsheet with ".xlsx" extension. So there is conflict between the file extensions.
I have saved the file with .xls then imported it. In this case p6 is not recognising the file and all the option to import activities or resources, etc were disabled.
Conflict of file extension might be a reason?
Member for
16 years 3 monthsUnder the security profile
Under the security profile under global profiles you need to make sure that the import XLS box is checked
Member for
16 years 7 monthsI am not a superuser though i
I am not a superuser though i have the global privilege and responsible manager assigne to me. So that would be the reason <AdminSuperuser>.
Thank you very much Santosh
Member for
20 years 6 monthsIt has to do with the
It has to do with the database security privileges for you. To import XLSS files you need both the Global privilege to import (which you must have as you get this far), and also be a Project Super User as the project security profile assigned to the responsible manager of that project.
You'll need to contact whimever administers the users in the P6 database you're working in to sort it out.